Water
Data centers are using up precious water resources across the country, with a single data center consuming as much water as a city of 50,000 people. Tech companies report record water consumption figures due to their growing data center footprints, even as they build more data centers in water-scarce locations. These numbers are also likely an undercount, as water for construction, cooling, and energy infrastructure is rarely considered in projections of data center water use. Claims that projects will be “water positive” do not replenish stressed aquifers, but refer to nominal fees paid by companies for water stewardship projects elsewhere.
Local Interventions
Local governments can pass water ordinances that limit the impacts of data centers and restrict data center development when proposals do not work in the community’s best interest.
Define Large-Quantity Water Users
Large-quantity water users should be defined as those whose water use equals or exceeds 10,000 centum cubic feet (ccf), equivalent to 7,480,000 gallons per month. To give a Benchmark: Project Blue, an Amazon hyperscaler data center in Tucson, Arizona, publicly projected they would use an average of 283 million gallons of water per year. (This […]
Read more
Large-quantity water users should be defined as those whose water use equals or exceeds 10,000 centum cubic feet (ccf), equivalent to 7,480,000 gallons per month.
To give a Benchmark:
Project Blue, an Amazon hyperscaler data center in Tucson, Arizona, publicly projected they would use an average of 283 million gallons of water per year. (This equates to approximately 23 million gallons, or 31,000 ccf, per month.) This calculation suggests that 10,000 ccf per month would capture hyperscaler data centers.
Establish Application Process for Large-Quantity Water Users
Require all large-quantity water users to submit an application for substantial water usage. Cities must reserve the right to determine that the applicant’s use would be incompatible with the city’s available resources and reject the application. Data centers should be presumed rejected unless the developer is able to prove robust and effective water-sustainability measures. Strong […]
Read more
Require all large-quantity water users to submit an application for substantial water usage. Cities must reserve the right to determine that the applicant’s use would be incompatible with the city’s available resources and reject the application. Data centers should be presumed rejected unless the developer is able to prove robust and effective water-sustainability measures.
Strong example
Aurora, Colorado, stipulates that high-water-use industries projecting consumptive water demands above certain thresholds cannot be developed unless water sustainability measures are taken.1
Require Comprehensive Accounting of Projected Water Usage
Applications must include the data center’s projected water usage. Applicants must be required to account for all water uses, including water used in data center construction, server cooling, facility cooling (including cooling towers), and other ancillary water uses. Most data center projections currently do not account for the water facilities will use to cool their […]
Read more
Applications must include the data center’s projected water usage. Applicants must be required to account for all water uses, including water used in data center construction, server cooling, facility cooling (including cooling towers), and other ancillary water uses. Most data center projections currently do not account for the water facilities will use to cool their infrastructure (including server cooling and facility cooling), which consumes a significant amount of water,1 as well as construction.
example
Illinois proposed SB 2181, requiring annual water consumption reporting for data centers broken out by month. The bill specifically calls out that water used for cooling must be included. (“‘Water consumption’ means the total amount of water consumed by a data center, including water used for cooling, measured in gallons.”)
Weak Example
California AB 93 (signed into law) mandates that new data centers must provide an estimate of their expected water use when applying for a city or county license. However, the legislation does not specify that all water uses must be included in this report, creating a loophole to exclude water used for cooling, construction, or other ancillary use cases.
- Pengfei Li et al., “Making AI Less ‘Thirsty’: Uncovering and Addressing the Secret Water Footprint of AI Models,” arXiv, March 26, 2025, https://arxiv.org/pdf/2304.03271. ↩︎
Require Comprehensive Accounting of Projected Water Sources
Increasingly, data centers are tapping into freshwater resources. Applicants must specify their water footprint, including blue sources (surface water and groundwater), piped sources (municipal water), and gray sources (purified reclaimed water). For blue sources, data centers must break down their expected sourcing of surface water and groundwater.
Read more
Increasingly, data centers are tapping into freshwater resources. Applicants must specify their water footprint, including blue sources (surface water and groundwater), piped sources (municipal water), and gray sources (purified reclaimed water). For blue sources, data centers must break down their expected sourcing of surface water and groundwater.1
- Miguel Yañez-Barnuevo, Data Centers and Water Consumption, Environmental and Energy Study Institute, June 25, 2025, https://www.eesi.org/articles/view/data-centers-and-water-consumption. ↩︎
Require Submission of a Water-Conservation Plan
Large-quantity water users must submit a water-conservation plan. Require independent review to evaluate whether the water-conservation plan will reduce the consumption of water, over what time period, and the impact this will have on residents and the environment. Options include the following: Water Efficiency Measures Require data centers to minimize water demand through efficiency measures […]
Read more
Large-quantity water users must submit a water-conservation plan. Require independent review to evaluate whether the water-conservation plan will reduce the consumption of water, over what time period, and the impact this will have on residents and the environment. Options include the following:
Water Efficiency Measures
Require data centers to minimize water demand through efficiency measures such as efficient airflow to reduce overall cooling needs, closed-loop cooling systems, and immersion cooling.
Water Replacement
Ordinance must specify that water should be fully replaced. The water replacement should benefit the watershed that blue sources are being drawn from.
Recycled Water Offset Requirements
Require large-quantity water users that consume on average more than 100,000 gallons of water per day for at least five days out of the year to offset their use by using recycled or conserved water for at least 50 percent of their water demand.
Minimum viable example
Phoenix, Arizona, requires large-quantity water users that consume more than 500,000 gallons of water per day to offset this by using recycled or conserved water for 30 percent of their water demand.
Note: Cities can require data centers to invest in infrastructure to meet recycled water requirements. This requirement will depend on a jurisdiction’s recycled water-treatment facilities, infrastructure, and goals.
Specify Requirements Around Liquid Cooling Versus Evaporative Air Cooling
Data centers in water-scarce areas may consider prohibiting evaporative air cooling techniques. This is because cooling data centers is extraordinarily resource intensive. There are generally two ways data centers can cool their servers: server liquid cooling (a process that delivers a liquid coolant directly to the graphics processing units, and that does not consume water) […]
Read more
Data centers in water-scarce areas may consider prohibiting evaporative air cooling techniques. This is because cooling data centers is extraordinarily resource intensive. There are generally two ways data centers can cool their servers: server liquid cooling (a process that delivers a liquid coolant directly to the graphics processing units, and that does not consume water) and air cooling (which uses water evaporation and is therefore a more water-intensive method). Some data centers also use cooling towers to cool their facilities; this method is very resource-intensive. While technology may change over time, cities should first assess whether data centers are worth the resource extraction required.1
Note: This distinction is not intuitive! Liquid cooling techniques use little to no water, and air cooling techniques use significant amounts of water.
Strong example
The Southern Nevada Water Authority adopted a moratorium on new evaporative cooling systems in commercial and industrial buildings because they are highly water intensive.
- Yañez-Barnuevo, Data Centers and Water Consumption. ↩︎
Require Data Centers to Pay for All Upfront Infrastructure Costs Related to Their Water Usage
While certain jurisdictions may have the necessary water infrastructure in place to service large-quantity water customers such as data centers, other jurisdictions may need to extend water and sewer infrastructure to serve new customers. Public utilities often pass these costs onto ratepayers, which can lead to higher water bills. This is particularly relevant for rural […]
Read more
While certain jurisdictions may have the necessary water infrastructure in place to service large-quantity water customers such as data centers, other jurisdictions may need to extend water and sewer infrastructure to serve new customers. Public utilities often pass these costs onto ratepayers, which can lead to higher water bills. This is particularly relevant for rural communities, where existing water infrastructure may be lacking.
Cities must demand that each data center pay 100 percent of estimated public infrastructure costs related to its water usage, with a particular focus on infrastructure upgrades needed to support the data center. This can be done through an annual Infrastructure Impact Fee deposited into a restricted fund used for local water infrastructure, conservation, and drought resilience projects.1
- Thanks to the Southeast Climate and Energy Network for crafting this policy recommendation. ↩︎
Require Water-Quality Testing and Reporting
Require that data centers test and publicly report water quality to ensure it remains safe, with a binding commitment to cleaning it up if it is not.
Read more
Require that data centers test and publicly report water quality to ensure it remains safe, with a binding commitment to cleaning it up if it is not.
Require Continued Transparency Mechanisms
Require that water consumption numbers and sourcing be made public in monthly reporting. Without transparency, effective enforcement of approvals based on water use and addressing harms will be more difficult. Reporting should include the following: This information must be submitted to the local agency overseeing the permitting process to ensure compliance with the terms of […]
Read more
Require that water consumption numbers and sourcing be made public in monthly reporting. Without transparency, effective enforcement of approvals based on water use and addressing harms will be more difficult. Reporting should include the following:
- Average monthly water usage, including cooling and ancillary uses
- Water-conservation-plan reporting
- An assessment of whether water demands require tapping surface or groundwater
- An assessment of whether potable water will be used
This information must be submitted to the local agency overseeing the permitting process to ensure compliance with the terms of the conditional permit. Information should also be reported to a state agency that gathers and discloses this information online. For more information about how states can track and publish these metrics online, see Establish a Statewide Clearinghouse.
Ensure Water Applications and Plans Are a Matter of Public Record
Ensure that the water-service applications and water-conservation plan are public records subject to disclosure under the state’s public records law. Stipulate that this information does not constitute a trade secret subject to exemption from disclosure.
Read more
Ensure that the water-service applications and water-conservation plan are public records subject to disclosure under the state’s public records law. Stipulate that this information does not constitute a trade secret subject to exemption from disclosure.
Levy Mandatory Taxes on Water Use
Tax the water usage with no exemptions, and increase the daily rate during droughts. Require that money be funneled into either water conservation projects or local infrastructure. Weak example Corpus Christi, Texas, taxes water usage, but only in droughts with opt-out provisions for large-volume industrial customers. This would allow data centers to opt out of […]
Read more
Tax the water usage with no exemptions, and increase the daily rate during droughts. Require that money be funneled into either water conservation projects or local infrastructure.
Weak example
Corpus Christi, Texas, taxes water usage, but only in droughts with opt-out provisions for large-volume industrial customers. This would allow data centers to opt out of drought surcharge fees and undermine the mitigation tactic.
Establish Strong Enforcement Mechanisms for Violations
The large-quantity water user must not voluntarily pledge to have a water-conservation plan, but actually enact it. Water-conservation plans must be legally binding. The city must build in enforcement mechanisms to enforce water usage and water-conservation plans. To implement the strongest penalty, water service should be shut off for violations. Nominal fines for violating a […]
Read more
The large-quantity water user must not voluntarily pledge to have a water-conservation plan, but actually enact it. Water-conservation plans must be legally binding. The city must build in enforcement mechanisms to enforce water usage and water-conservation plans. To implement the strongest penalty, water service should be shut off for violations. Nominal fines for violating a water permit mean nothing to hyperscale data centers.
